English (UK)
Flow Measurement to create a Sewage Master Plan
Channel Networks - Portable Measurements

Application
- Concrete pipe DN 500
- Partially filled
- High discharge dynamics
- Risk of sedimentation
Definition of tasks
- Detection of precipitation, flow, level and flood covering a minimum period of 3 months to create a Sewage Master Plan
- No main power available
- High discharge dynamics from lowest levels up to complete flood of the channel system
- Sound waves due to pump activities
- ASCII a preferred data format
Advantages
- Accurate flow detection even with varying levels thanks to the combined use of different level sensors utilising different measurement principles.
- Measurement results are easy to evaluate in all common applications thanks to using the standard ASCII data format.